patching...
Welcome back, Patch Blogger!

When Will Construction in the Town Center Wrap Up?

The underground utility project is finishing up work in the public right-of-way.

 

Welcome to You Ask, Patch Answers, a column where you ask a question about anything going on in town and we'll try to get you an answer. If you have a question, send it to krista@patch.com.

Question:  I am beyond sick of all the traffic in the center of town. When is the undeground utility project going to finish up?

Answer: Town Manager Paul Cohen said work in the streets is finishing up, and should be done with final paving around June 1, meaning traffic will ease after that. Cohen said work will then move to the sidewalks and the rail trail crossings, which shouldn't impede traffic as much as the project currently has been. After that work is done, phase one of the project will be finished up, Cohen said.

Cohen said there is no specified completion date for all phases of the underground utility project in the town center.  The constraint on the project schedule, he said, is the collection of surcharges on traditional land line telephone service that funds the costs for the suppression of the Verizon lines.

"The advent of wireless telephone and cable/internet telephone service has significantly reduced the number of traditional land line telephone service customers, thereby reducing the collection of these funds," he said.

About this column: You Ask … Patch Answers is a column for locals looking for answers to community questions. Related Topics: You Ask...Patch Answers and underground utility project

Comment_arrow

Maria Karafelis

8:17 am on Wednesday, May 23, 2012

Yes, Jim phase one. The work in the center has been broken down into phases, phase one is a good size project, and the biggest hold up was the poles and working with the utilities to get them moved to continue with the project. It has been a long process, and I cannot wait to see it finished, The July 4th celebration this year is going to be beautiful with all of the work that has been done and all of the hard work that is being done behind the scenes that no one sees.

Peter Gilman

7:46 am on Wednesday, May 23, 2012

Exactly! How many phases are there and what does each accomplish? What is the end goal? Costs? On budget? State or Fed money?

Reply

Krista Perry

9:13 am on Wednesday, May 23, 2012

I updated the body with some more info from the town manager; there is no final completion date yet because of a Verizon issue.

Reply
Comment_arrow

Maria Karafelis

3:01 pm on Wednesday, May 23, 2012

Verizon has been the major contributors to the hold up. If I am not mistaken when this was presented at town meeting, I think there were four stages, which involved going down into the center. If memory serves me correctly Mr. Cohen mentioned that the additional phases were going to be tabled for the time being because of all the issues the utilities and Phase 1. I can't speak to the funding, it's been so long other than the surcharges from Verizon, I really don't remember. Maybe Krista you can ask Mr. Cohen specifically how the funding of this project works other than for the Verizon piece of it.

jtalexander

10:45 am on Wednesday, May 23, 2012

I have two additional questions for our town manager as they relate to the project.
Why can't the put a sign out on rt 3 at Drum Hill informing people of construction in the center of town, thus giving some people who use north road as a pass through to 495 or even through town to around and why can't the police who are getting paid, do more that stand around. The other day, they closed north road at St Mary's and directed all traffic down Fletcher, but did not bother to have someone at 110 direct traffic to turn onto 110. I can't count the times I see police who are being paid, talking on phones and each other.

Reply

Ned Blue

11:33 am on Wednesday, May 23, 2012

It's great to see that others in Chelmsford have already realized that a Verizon land line isn't worth the money they charge. We switched to a very inexpensive cable add-on (MagicJack) about a year ago, and we couldn't be more happy. The call clarity is excellent, and it costs less than 10% of what Verizon was charging. Apparently a lot of other people had the same idea, and that's why they aren't raising enough money with their ridiculous surcharge! I would encourage everyone else in town to do the same. Verizon's service isn't needed, and the project will never get finished anyway. Don't be the last person in town paying for that surcharge, because you will end up footing the entire bill all by yourself over the next 20 years!

Reply
Comment_arrow

Tony

1:21 pm on Thursday, May 24, 2012

I hate to be the bearer of bad news, but Verizon isn't the utility with the surcharge, it's National Grid. So I guess you'll be paying for the buried cable like the rest of us if you are on the electric grid.

Comment_arrow

Ned Blue

9:49 am on Friday, May 25, 2012

Krista's article explained that according to Cohen, "The constraint on the project schedule...is the collection of surcharges on traditional land line telephone service that funds the costs for the suppression of the Verizon lines." Tony, I think you are saying that you don't believe her statement to be true. I guess we will have to let Krista comment in whether she still believes that her statement is accurate. Is Verizon collecting surcharges to fund suppression of the lines?

Comment_arrow

Tony

11:15 am on Friday, May 25, 2012

Ned: No. I agree with what Krista said. There's no doubt that Verizon landlines have been effected by competition from cellphones, iphones, FIOS, Comcast, etc. What I should have said was that National Grid, Comcast, and Verizon have all collected surcharges since inception of the agreement with the town to bury cables and that we already have paid for it over many years. I believe the Verizon surcharge was a dollar, or two, per month for an average homeowner. I'll have to check to see if Verizon is still collecting. If they are, then there's validity to what Cohen has indicated is the holdup. Verizon still needs to capture whatever dollar diffference there is between what they estimated they needed and what has been collected. I don't think it's a large amount of money but Verizon, by agreement, has the right to wait until it has the cash in hand. I don't think that the parties to the agreement ever saw the future impact of technology on landline services. For example, FIOS itself competes with landlines, but I don't think that was ever forecasted as part of the deal. I don't believe that FIOS customers were required to pay the surcharge and, in addition, Verizon landline revenues were lost by the replacement of existing lines in homes, businesses, etc., that switched over to FIOS.

jtalexander

11:25 am on Thursday, May 24, 2012

Krista,

I am still waiting for an answer, or is that you do not want to upset your facebook buddy, Paul.

Reply
Comment_arrow

Krista Perry

11:34 am on Thursday, May 24, 2012

My apologies JTAlexander, I did not see your questions. I will do my best to get you an answer.

Comment_arrow

Maria Karafelis

1:13 pm on Thursday, May 24, 2012

Actually Krista the question was in my last post, I did not send it directly to you. Sorry, for the confusion.

Krista Perry

11:49 am on Thursday, May 24, 2012

In terms of signage, the work in the town center will be finished within the next week or so. Usually the town does place sign boards for major scheduled traffic issues, such as nighttime road closures for paving.

As for the police question, we are having a live chat with Police Chief James Murphy on Tuesday at noon. Let's ask him about that.

Reply

Maria Karafelis

2:28 pm on Thursday, May 24, 2012

Tony;
The surcharge from National Grid on your electric bill was removed about 9 months to a year ago. Verizon's problem is they have too much competition for services, as a matter of fact as of last year they decided not to put FIOS in Lowell because it was not cost effective for them.

Reply
Comment_arrow

Tony

6:26 pm on Thursday, May 24, 2012

Maria, my comment to Ned was only intended to make him aware that Verizon wasn't the only utility that had been collecting the surcharge so nothing was really being saved in this regard by dumping the service. As I think back to a conversation I had with Bernie Lynch some time ago, we spoke more about the reticence of National Grid to move forward without collecting sufficient funds to complete the project. I should have made it clearer that Comcast, Verizon, and National Grid were all allowed to collect the additional fee.

Maria Karafelis

8:09 am on Friday, May 25, 2012

Sorry, I misunderstood. Now I see where you were going.

Reply
Comment_arrow

Tony

11:31 am on Friday, May 25, 2012

Maria, This is an interesting project to follow since it shows how difficult it is to bring a government/private venture to fruition. It's history is fascinating and there were many "bumps in the road." I know that Mr. Lynch was frustrated many times trying to get this thing implemented literally htting the proverbial "stonewall" each time he tried to negotiate a start date with National Grid. My hat's off to Mr. Cohen, et al., because, quite frankly, I didn't expect to see this happen in my lifetime knowing what Mr. Lynch was going through. I think that the improvements to Chelmsford Center will far outweigh any of the small surcharges we paid. This is a beautification project that will not only be a source of local pride, but an enhancement to the livability and overall appeal of Chelmsford and a positive influence on future property values.

Ned Blue

4:55 pm on Friday, May 25, 2012

To be completely honest, I don't expect the completion of this project to "happen in my lifetime." As Cohen said, there is "no specified completion date." I also find it absurd to be paying fees to the very people who created this eyesore in the first place. National Grid already took more money from residents than is actually needed to complete their part of the work, and yet the work isn't getting done, and nobody knows when it might be completed. Verizon is still collecting more for their part. Everyone is getting what they want out of this deal except the residents. The residents of Chelmsford want to see this work completed or they want their money back! For my part, I am making sure that I don't send another dime to Verizon to continue this debacle. The whole thing appears to have been mismanaged, and it is quickly becoming a public embarrassment for the town.

Reply

Paul

12:18 am on Tuesday, June 12, 2012

The project will be done when the town has sucked every last nickle from your pocket. Expect the meal tax to go up in the near future. Gotta pay big money for those police officers to talk on their cell phones.

Reply

Leave a comment